NEP based in Bracknell are a leading provider of outside broadcasting. NEP required additional office space to an existing first floor office with a workshop/storage area underneath.

What we did

NEP suspended ceiling installation project by HMF

A mezzanine floor with fire rated protection including a 1 hour fascia, 1 hour column casings & 1 hour suspended ceilings were installed by HMF.

On the mezzanine the first floor office ceiling was hung from a 15m high roof which involved a complex subgrid.

New LED lighting with PIR controls was installed & new carpet laid.

285m² of additional office space was created linked with a new breakthrough by HMF into the existing offices.

Double skin steel partitions were specified to keep mess and dust to a minimum in areas of all their technical lorries with complex external broadcasting kit.

NEP mezzanine floor installation and fit out by HMF

A separate partitioned area under the existing concrete mezzanine created a new storage space with anti-static vinyl raised floor tiles with an access ramp for trolleys.

All the works were constructed in a busy operational warehouse in a 10 week programme.

Get a free quote for your next project

Tell us about your project, so we can organise a free quote.

We will get in touch with you as soon as possible. We will not transfer your information to any third parties.

Products

We'll be in touch!