HMF designed a conveyor system to transport products from ground floor to mezzanine and then mezzanine to ground floor which incorporated a new powered incline belt conveyor as well as conventional gravity roller conveyors to the ground and first floor.
HMF then extended the existing fire alarm system to BS 5839 to cover the building and provided emergency lighting to BS 5266.
HMF provided partitions to form protected fire escapes as well as modifying the existing office and welfare areas.
Once HMF had taped, jointed and decorated the new surfaces it was time for the new PSS Shelfspan to be fitted.
This Longspan was 2.44 miles long giving Cotswold Outdoors considerable additional expansion for picking operations within the composite building.