As the mezzanine was positioned in the busy warehouse & packing area it was decided that the project should be done over a long weekend to minimise disruption to the client as they were very busy during the pandemic.
The mezzanine floor & pallet racking were dismantled & re-sited in a 7 day programme with HMF organising everything from plant to safely dismantle & re-erect the mezzanine floor, transport between the 2 sites, lighting, emergency lighting & fire alarm works including stripping out the existing fittings & re-using at the new site. This also included making the existing building safe & re-installing the fire alarm ready for the new tenants.
The mezzanine itself was modified on site to fit the new building with a bay of joists being cut down & re-drilled to narrow the floor where the goods in door was positioned. The mezzanine floor also had to be cut around some building piers to ensure a good fit.